| Clients & Projects |
|---|
|
![]() Tunnel Before |
![]() Tunnel After |
![]() Finished Manhole |
![]() Waste Treatment Plant |
![]() Aquaduct |
![]() Settling Tank |
| Installation Date - (1993) |
|---|
| Quantity (Size, Diameter, Length) |
Re-Coated structural steel with 100% solid epoxy - (Inspected in 2001 - in good condition) |
| Location | Anheuser-Busch Co. Merrimack, NH |
| Client/Contact Person | Jim Trainor, Anheuser-Busch 221 Daniel Webster Highway Merrimack, NH 03054 (603) 889-6631 |
| Total Construction Cost | $1,000,000.00 |
| Years in Service | 8 Years |
| Installation Date - (1994-2001) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was the only one of six products tested to pass the 5-year study in DeKalb County, GA 600 manholes were tested |
| Location | East Snapfinger Rd. Basin DeKalb, GA |
| Client/Contact Person | Rick Daniels, DeKalb County 1580 Roadhaven Drive Stone Mountain, GA 30083 (770) 621-7200 |
| Total Construction Cost | to date - $1,000,000.00 **$2.0 million in progress |
| Years in Service | In Progress |
| Installation Date - (1995) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system successfully repaired 4 pump stations subject to extreme H2S and I/I problems where the Raven Lining and Quadex System had previously failed |
| Location | City of Sarasota Lift Stations Sarasota, FL |
| Client/Contact Person | Rick Ray City of Sarasota Public Works 1750 12th St. Sarsota,Fl. 34236 (941) 955-2325 |
| Total Construction Cost | $190,000.00 |
| Years in Service | 6 years |
| Installation Date - (1995) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was installed in sanitary manholes |
| Location | Town of Marblehead Water & Sewer Commission Marblehead, MA |
| Client/Contact Person | Dana Snow, Town of Marblehead Water & Sewer Commission P.O. Box 1108, Marblehead, MA 01945 (781) 631-2694 |
| Total Construction Cost | $136,000.00 |
| Years in Service | 6 years |
| Installation Date - (1997) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system, in a paid competition, successfully lined 200' of 60" tunnel in low flow conditions, and 2 large under-ground siphon stations. The competitive product provided by Linabond was completely destroyed in this study by infiltration problems and H2S attack. At the end of the two year study, the WES system was in like new condition. |
| Location | Miami-Dade Sewer Project Miami-Dade County, FL |
| Client/Contact Person | Pat Murray (formerly with Rust Environmental) 1020 N. Broadway, Suite G-12 Milwaukee, WI 53202 (414) 270-4208 |
| Total Construction Cost | $180,000.00 |
| Years in Service | 4 years |
| Installation Date - (1997-2000) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was installed in manholes and digesters and E.Q. tanks |
| Location | Anheuser-Busch Co. Baldwinsville, NY |
| Client/Contact Person | Robert Jasper - Anheuser Busch 2885 Belguim Road Baldwinsville, NY 13027 (315) 635-8610 |
| Total Construction Cost | $400,000.00 |
| Years in Service | 4 years |
| Installation Date - (1997-2001) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system successfully coated, over a 4 year period, 150 manholes, 1 wastewater treatment plan, and 4 pump stations in Owensboro, KY, and was recently chosen to repair and replace a failed system of Raven Lining's ultrahibuild system that was destroyed in a low PH environment |
| Location | Manhole Restoration Project Owensboro, KY |
| Client/Contact Person | Mr. Dean Behnke City of Owensboro, KY Regional Water Resource 2101 Grimes Avenue Owensboro, KY 42303 (270) 687-8459 |
| Total Construction Cost | $300,000.00 |
| Years in Service | 4 years |
| Installation Date - (1997) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was installed in sanitary manholes. |
| Location | Kodak Park, CO |
| Client/Contact Person | Tim McCarthy Eastman Kodak Windsor, CO (757) 879-3641 |
| Total Construction Cost | |
| Years in Service | 4 years |
| Installation Date - (1997-Present) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system has restored over 4,500 manholes in Jefferson Cnty, AL, and is one of only two restoration processes approved in Jefferson County, AL |
| Location | Jefferson Cnty Sewer Restoration Birmingham, AL |
| Client/Contact Person | Mr. John Wanhatalo, Hailey-Rast 2901 Shannon-Oxmoor Rd. Birmingham, AL 35201 (205) 942-6888 |
| Total Construction Cost | $3.2 million to date **$1.5 million in progress |
| Years in Service | In Progress |
| Installation Date - (1998) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was installed in wastewater treatment plant biofilters |
| Location | Mandarin Wastewater Treatment Plant Jacksonville, FL |
| Client/Contact Person | Nolan Hake Danis Construction (904) 260-1976 |
| Total Construction Cost | $541,830.00 |
| Years in Service | 3 years |
| Installation Date - (1999) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system was installed in crosspassages of the subway. |
| Location | Metro Red Line North Hollywood, CA |
| Client/Contact Person | Al Watson R.A. Watson Company 506 Main Street ElSegundo, CA 90245 |
| Total Construction Cost | $400,000.00 |
| Years in Service | 3 years |
| Installation Date - (1999) |
|---|
| Quantity (Size, Diameter, Length) |
The WES system successfully restored complete sewage treatment plant lift stations, digesters, and equilization basins where a previously installed system by TNEMEC had failed in a low PH environment |
| Location | Sewer Treatment Plant Upgrade Anheuser-Busch Co. Cartersville, GA |
| Client/Contact Person | Bill Kutosky, Anheuser-Busch Co. 1 Busch Place 2816 South 3rd Street St. Louis, MO 63118 (314) 577-2916 |
| Total Construction Cost | $2,000,000.00 |
| Years in Service | 2 years |
| Installation Date - (2001) |
|---|
| Quantity (Size, Diameter, Length) |
Complete restoration of equilization basins, grit chambers and sludge blend tanks (all holding vessells in the plant) |
| Location | Wast Water Treatment Plant #1 Newport, RI |
| Client/Contact Person | Mr. Brian Corbett, Earth Tech 250 Connell Highway Newport, RI (401) 849-2637 |
| Total Construction Cost | $1,400,000.00 |
| Years in Service | In Progress |